Four Oil Well Pad Case Study

IPT Engineers Designed, Procured and Installed Production Equipment for a Four Oil Well Pad in Morgan County, Colorado

At IPT Well Solutions, we specialize in delivering top-tier engineering and wellsite supervision services. Our recent project in Morgan County, Colorado, for a four oil well pad showcases our commitment to excellence.

The Challenge

We were tasked with designing and installing a production storage facility within a strict client-specified timetable during winter. Our engineers determined gas lift as the primary artificial lift mechanism for the project.

The Approach

Our team designed, procured, and installed production storage, gas lift compression, and high-line electrical equipment. We refurbished and used existing industry-standard equipment to cut costs and expedite the project timeline. Safety procedures were strictly enforced, and sound and wind walls were constructed to protect the equipment from winter weather.

The Solution

During operations, we found higher water production than estimated. After tests and reviews, we recommended and installed a second gas lift compressor, resulting in improved well performance and increased production.

The Result

We completed the project six days ahead of schedule, allowing production operations to start immediately after well completion.

Call to Action

Want to learn more about this project and our innovative solutions? Download our full case study below or contact us for more information!

Like this article? Share It Using the Links Below:

© Copyright 2022 New IPT Inc. All Rights Reserved.